Facts and figures
- Joint-venture companies – Equinor/Polenergia (each holding 50%)
- Capacity 1440 MW (720 MW x 2)
- Equinor is the operator in the development, construction and operation phases
- Polenergia is responsible for obtaining all permits and management of local affairs
- The operation period is 25 – 30 years
- Two offshore substations
- One onshore substation
Design data: | MFW Baltyk II | MFW Baltyk III |
---|---|---|
Area of the farm covered by the permit [km²] | 122 | 119,52 |
Installed power capacity [MW] | 720 | 720 |
Water depth [m] | 23-41 | 25-39 |
Distance from the shore [km] | 37 | 22 |
Length of offshore cables [km] | 60 | 65 |
Length of onshore cables to onshore substation [km] | 10 | 10 |
Distance from the onshore substation to the connection to the TSO grid [km] |
4 | 4 |
Initial timeframes | MFW Baltyk II | MFW Baltyk III |
---|---|---|
Award of the Contract for Difference | 2021 | 2021 |
Building permit | 2023 | 2023 |
Commencement of electricity generation | 2026 | 2026 |